KPOC starts gas production from Kebabangan field

Share this post
KPOC successfully started gas production from the Kebabangan (KBB) platform on 11 Nov 2014, which also marked the commencement of the production phase at the Kebabangan gas field.

The production from the KBB field is expected to ramp up to 500 MMSCF per day by April 2015. The field is located offshore Sabah, Malaysia and is part of the KBB Cluster fields and future tie-ins from other nearby fields.

The KBB platform is an integrated production facility designed and built as a hub with gas, condensate and crude oil processing facilities to cater production from the KBB cluster fields and future tie-ins from other nearby fields.

The platform, measuring approximately 18,000 metric tonnes in weight and 39 metres in height, is one of the largest offshore structures ever built in Malaysia. It is designed with capacity to process up to 825 million standard cubit feet of natural gas, 80 000 barrel of crude oil and 22,000 barrels of condensate daily.

Hydrocarbons from the platform will be transported through a pipeline to the Sabah Oil and Gas Terminal located onshore Kimanis, Sabah.

KPOC is a joint operating company comprising PETRONAS Carigali Sdn Bhd (40%) ConocoPhillips Sabah Gas Ltd (30%) and Shell Energy Limited (30%).

this achievement is yet another testimony to get great collaboration , dedication and commitment by all parties involved in the project.

KPOC's CEO, Mr. Kannan Annamalai said, 'we are extremely please and proud to deliver this project on schedule and within budget whilst upholding Quality, Health, Safety and Environment standards.

"this success is attributed to KPOC's highly competent and motivated staff and the excellent support from the collaboration with PETRONAS, government agencies and KPOC shareholders. The fact we delivered this project in November 2014 which is also the month of KPOC's 7th anniversary makes this achievement sweeter', he added.

President of PETRONAS Carigali Sdn Bhd, Datuk Mohd Anuar Taib commented, "Gas from the KBB field, a stranded gas field discovered in 1994, is finally able to be commercially developed through the PETRONAS LNG Complex in Bintulu, providing benefits for all - PSC Contractors, PETRONAS, MLNG PArtners and customers, and both Sabah and Sarawak states'.

Mr. Mark Wheeler, President of ConocoPhillips Malasysia said, " We are especially pleased with achieving KBB first gas as it marks the major project start up for ConocoPhillips Malaysia this year. The project will contributed to the company's plan to deliver annually three to five percent production and margin growth over the coming years'.

Mr. Iain Lo, SHell Malaysia Chairman added, " KBB is a significant gas resource for Malaysia, the start of production is therefore an important and exciting milestone for KPOC. We are please to continue supporting KPOC as it develops the remaining KBB Cluster fields'.

Issued by:-

Kebababangan Petroleum Operating Company Sdn. Bhd.
November 2014